The Poet Residence Celebrates the Completion of Bored Pile and Diaphragm Wall Works – A Major Milestone Marking the Start of Official Construction
On June 7, 2025, the Investor – Phuc Thanh An Real Estate Joint Stock Company and the contractor Tam Dac E&C organized the completion ceremony for the bored pile and diaphragm wall package of the Ho Xuan Huong Apartment project (The Poet Residence). The ceremony was attended by representatives of the Investor, the contractor, and the supervision consultant.
On June 7, 2025, the Investor – Phuc Thanh An Real Estate Joint Stock Company, together with the contractor Tam Dac E&C, held a ceremony to mark the completion of the bored pile and diaphragm wall construction phase at the Ho Xuan Huong Apartment project (The Poet Residence). Attendees included:
Representing the Investor: - Ms. Pham Thi Hong – Chairwoman of the Board of Directors;
- Mr. Nguyen Ba Di – General Director
Representing the Contractor: - Mr. Nguyen Minh Tri – Director of Tam Dac E&C;
Representing the Supervision Consultant: - Mr. Vu Viet Phuong – Chief Supervision Consultant.

As of June 7, 2025, the contractor has successfully completed 70 bored piles and 197.45 meters of diaphragm walls. Speaking at the completion ceremony, Mr. Nguyen Ba Di – General Director highly praised Tam Dac E&C contractor for ensuring safety, quality, and progress as required by the Investor.

The Ho Xuan Huong Apartment project is built at 95, 97, 99 Ho Xuan Huong Street, Da Nang City; featuring a scale of 2 basements, 25 above-ground floors, and a roof level; with a total gross floor area of 30,080.8 square meters... under Construction Permit No. 414/GPXD dated April 11, 2025.